Z--CERC A3 Single Phase Electrical Panel Upgrade

Posted Date: Feb 20, 2025
Due Date: Mar 15, 2025
Awarded Date: No Awarded Date
SetAside Type
Total Small Business Set-Aside (FAR 19.5)
Solicitation ID Solicitation Title Solicitation Office
140G0125Q0052 Z--CERC A3 Single Phase Electrical Panel Upgrade
Synopsis
*Amendment 004* - Q&A
*Amendment 003 - Additional site visit*
*Amendment 002 - Q&A and update SOW*
*Amendment 001 - Q&A*

The U.S. Geological Survey Columbia Environmental Research Center (CERC) has a requirement for an electrical upgrade to include but not limited to removing and replacing the existing building main single-phase 1200-amp disconnect with a new 600-volt 1200-amp distribution panel at the Columbia Environmental Research Center (CERC) in Columbia, MO. The contractor shall provide all labor, material, tools, equipment, and supervision necessary.

The magnitude of construction is between $100,000 and $250,000.

Request for Quote (RFQ) 140G0125Q0052 will be issued on or about 2/6/2025 with written quotes .... Read More
Office Location Agency Name Solicitation Base Posting Type
US GEOLOGICAL SURVEY Combined Synopsis/Solicitation
SetAside Type
Total Small Business Set-Aside (FAR 19.5)
Solicitation ID Solicitation Title Solicitation Office
140G0125Q0052 Z--CERC A3 Single Phase Electrical Panel Upgrade
Synopsis
*Amendment 002 - Q&A and update SOW*
*Amendment 001 - Q&A*

The U.S. Geological Survey Columbia Environmental Research Center (CERC) has a requirement for an electrical upgrade to include but not limited to removing and replacing the existing building main single-phase 1200-amp disconnect with a new 600-volt 1200-amp distribution panel at the Columbia Environmental Research Center (CERC) in Columbia, MO. The contractor shall provide all labor, material, tools, equipment, and supervision necessary.

The magnitude of construction is between $100,000 and $250,000.

Request for Quote (RFQ) 140G0125Q0052 will be issued on or about 2/6/2025 with written quotes due on 2/28/2025. Upon award payment protections are .... Read More
Office Location Agency Name Solicitation Base Posting Type
US GEOLOGICAL SURVEY Combined Synopsis/Solicitation
SetAside Type
Total Small Business Set-Aside (FAR 19.5)
Solicitation ID Solicitation Title Solicitation Office
140G0125Q0052 CERC A3 Single Phase Electrical Panel Upgrade
Synopsis
The U.S. Geological Survey Columbia Environmental Research Center (CERC) has a requirement for an electrical upgrade to include but not limited to removing and replacing the existing building main single-phase 1200-amp disconnect with a new 600-volt 1200-amp distribution panel at the Columbia Environmental Research Center (CERC) in Columbia, MO. The contractor shall provide all labor, material, tools, equipment, and supervision necessary.

The magnitude of construction is between $100,000 and $250,000.

Request for Quote (RFQ) 140G0125Q0052 will be issued on or about 2/6/2025 with written quotes due on 2/28/2025. Upon award payment protections are required.

There will be a site visit. All contractors are .... Read More
Office Location Agency Name Solicitation Base Posting Type
US GEOLOGICAL SURVEY Combined Synopsis/Solicitation
An error has occurred. This application may no longer respond until reloaded. Reload 🗙