Synopsis

2/19/2025: add RFI Q/A, and attached 3 UFGS

2/12/2025:updated solicitation close date to 2/26/2025. Several RFIs still pending answering, and personel that can answer these questions will not return ot office till 2/19/2025. will post Q/A of RFI, and possibly updated SOW once available. 

2/11/2025: updated solicitation close date to 2/19/2025. Several RFIs still pending answering. will post Q/A of RFI once available. 

BASE ITEMS: Work includes but is not limited to:
1) Design and construct manhole benching and invert channels for WPB building manhole.
2) Inverts must be true to the sewer pipe invert .... Read More

Office Location Agency Name Solicitation Base Posting Type
US COAST GUARD Combined Synopsis/Solicitation
SetAside Type
Total Small Business Set-Aside (FAR 19.5)
Solicitation ID Solicitation Title Solicitation Office
31060PR250000070 Base Honolulu manhole sewer repair
Synopsis

2/11/2025: updated solicitation close date to 2/19/2025. Several RFIs still pending answering. will post Q/A of RFI once available. 

BASE ITEMS: Work includes but is not limited to:
1) Design and construct manhole benching and invert channels for WPB building manhole.
2) Inverts must be true to the sewer pipe invert elevation with smooth channels of uniform
cross section and slop, either straight or with a continuous curve between the inlet and
outlet of the pipes. Concrete inverts should be placed based on the dimension and details
of the contract plans and specification.
.... Read More

Office Location Agency Name Solicitation Base Posting Type
US COAST GUARD Combined Synopsis/Solicitation
SetAside Type
Total Small Business Set-Aside (FAR 19.5)
Solicitation ID Solicitation Title Solicitation Office
31060PR250000070 Base Honolulu manhole sewer repair
Synopsis

BASE ITEMS: Work includes but is not limited to:
1) Design and construct manhole benching and invert channels for WPB building manhole.
2) Inverts must be true to the sewer pipe invert elevation with smooth channels of uniform
cross section and slop, either straight or with a continuous curve between the inlet and
outlet of the pipes. Concrete inverts should be placed based on the dimension and details
of the contract plans and specification.
3) Contractor shall follow OSHA section 1926.953 safety requirements for confined space
entry before a manhole cover can be .... Read More